Site progress and project news from Whiteland developments in Gurgaon, newest first.

Site Progress

Latest Construction Updates

Whiteland Westin Residences
18 Sep 2026 · Whiteland Westin Residences

Westin Residences — tower-wise construction status, September 2026

Phase 1 towers (T2, T3, T4, T4A, T4B — 848 homes, all 3 BHK) have their superstructure up, with slabs rising floor by floor. Phase 2 (T1 and T5, 264 units) follows behind Phase 1. Phase 4 (T6 to T9, 352 four-bedroom homes) is at foundation stage, with excavation and raft casting underway. On-ground construction is split between KPIL and ACIL.

Read the full update View project
Westin Residences — construction update video, June 2026 — video thumbnail
14 Jun 2026 · Whiteland Westin Residences

Westin Residences — construction update video, June 2026

The developer’s official site walk-through of construction progress at Westin Residences, Sector 103, Dwarka Expressway, as of 14 June 2026.

View project

This website is operated by [PLACEHOLDER: Authorised marketing partner name], an authorised marketing partner of Whiteland projects (HARERA Agent Reg. No. [PLACEHOLDER: HARERA agent registration no.]). It is not the official website of the developer or of HARERA. Project RERA numbers are listed on each project page and can be verified at haryanarera.gov.in. All images are artist’s impressions; specifications, prices and availability are indicative and subject to change without notice. This is not an offer or contract. Read the full disclaimer.